| Typical application | Single production line with moderate inspection volume | Multi-shift line with mixed product sizes and regular changeovers | High-volume line where conveyor capacity and recovery time are priorities |
| Indicative throughput planning range | Up to 60 packs/min, depending on pack size and spacing | Up to 100 packs/min, depending on product and line configuration | Up to 150 packs/min, depending on product and line configuration |
| Inspection configuration to specify | Dual-energy imaging; confirm usable aperture and belt speed against the largest product | Dual-energy imaging with recipe management and integration to reject confirmation | Dual-energy imaging with line-control integration and defined restart and recovery procedures |
| Initial equipment budget | $280,000 | $420,000 | $620,000 |
| Installation, integration, and training allowance | $45,000 | $60,000 | $85,000 |
| Annual service and spare-parts allowance | $16,000/year | $21,000/year | $29,000/year |
| Annual energy and routine consumables allowance | $5,000/year | $7,000/year | $10,000/year |
| Illustrative 10-year lifecycle cost | $535,000 | $760,000 | $1,095,000 |
| Lifecycle cost calculation | $280,000 + $45,000 + 10 × ($16,000 + $5,000) | $420,000 + $60,000 + 10 × ($21,000 + $7,000) | $620,000 + $85,000 + 10 × ($29,000 + $10,000) |
| Planning availability assumption | 97.0% | 98.0% | 98.5% |
| FAT: low-density challenge samples detected | 94 / 100 (94%) | 97 / 100 (97%) | 98 / 100 (98%) |
| FAT: dense-material challenge samples detected | 98 / 100 (98%) | 99 / 100 (99%) | 100 / 100 (100%) |
| SAT: low-density challenge samples detected | 92 / 100 (92%) | 96 / 100 (96%) | 97 / 100 (97%) |
| SAT: dense-material challenge samples detected | 97 / 100 (97%) | 99 / 100 (99%) | 99 / 100 (99%) |
| Example FAT/SAT acceptance condition | Agree the contaminant types, challenge-piece dimensions, product recipes, test-pack positions, sample counts, and pass criteria before testing. Confirm results separately for each product family and operating speed. |
| Key selection trade-off | Lowest modeled cost; check whether performance and service coverage meet the site’s risk requirements | Middle-cost option; balance inspection performance, uptime provisions, and integration needs | Highest modeled cost; assess whether the additional capacity and availability justify the investment |